Construction of 3.500 ton - acid tank for Long Thanh Supephophat factory
IDICO - UDICO is the contractor to execute the Project “Construction of 3.500 ton - acid tank for Long Thanh Supephophat factory and auxiliary works” belonging to the package “3.500 ton - acid tank”.
Project scale includes tank foundation with 22,7mx2m diameter, reinforcement structure, foundation system, wall, with value of 3,35 billion VND.
Project was commenced to costruct on October 24th, 2013.
Costruction duration: 60 days
Construction location: Go Dau Industrial Zone - Long Thanh - Dong Nai
IDICO - UDICO has mobiled manpower and equipment for construction work. |