Project summary: * Investment licence: 47121000201 issued by Dong Nai People Committee dated April 4th 2009.
* Location : Tan Hiep Commune - Long Thanh District - Dong Nai Province.
* Total area: 29,81 ha.
* Project scale :

Eploitation reverse: 1.939.000 m3
Exploitaion method:480.000 m3 /year
Level ending exploitaion: cote +24m.
Slope angle ending exploitation: 300.
Exploitation duration: 05 year.
* Total investment: more than 30 billion VND. Soil area layout
IDICO - UDICO has so far coordinated with related agencies for the execution of land withdrawing, compensation and ressettlement support and site clearance (In accordance with the Decision No.1173/QD-UBND dated April 27th 2009 issued by Dong Nai People Committee) in order to exploit the mine in accordace with schedule in service of provide leveling and filling materials for highway projects and key traffc projects in the area. |